NEW QUESTION 25
In the SAP Best Practices Time Recording - Project-Based Services (J12) scenario, which of the following settings can be enabled via SSCUI Maintain Data Entry Profiles? Note: There are 3 correct Answers to this question.

  • A. Switch on or off the approval process
  • B. Enable the field 'Work Location' to allow users to enter work location when recording the time in timesheet application
  • C. Switch on the field 'All Project Phases' to enable timesheet posting to be made regardless of project status
  • D. Switch on the field 'Extensibility Mode' to enable the extensibility of the timesheet application
  • E. Enable the field 'WBS Element' to allow users to specify the project task they are recording time against

Answer: A,B,D

 

NEW QUESTION 26
What are the available options for service entry sheet creation? Note: There are 2 correct Answers to this question.

  • A. Manual creation after time recording approval
  • B. Import service entry sheets
  • C. Automatic creation via the billing plan schedule
  • D. Automatic creation upon time recording approval

Answer: B,D

 

NEW QUESTION 27
You are reordering purchase order items with reference to a purchasing document that already exists.
Which of the following documents can be used? Note: There are 3 correct Answers to this question.

  • A. A service entry sheet
  • B. A purchase contract item
  • C. An info record
  • D. An Intrastat report
  • E. A purchase order item

Answer: A,B,C

 

NEW QUESTION 28
In which implementation phase do you perform data load preparation?

  • A. Explore
  • B. Deploy
  • C. Prepare
  • D. Realize

Answer: A

 

NEW QUESTION 29
A customer needs detailed customization to the standard forms and email templates. What solution should the consultant propose?

  • A. Use the Adobe Livecycle Designer tool to edit a standard template
  • B. Use the Output Management apps to customize a standard template
  • C. Use the corresponding configuration items to modify elements of the form template
  • D. Create a custom UI with the Custom Fields and Logic app

Answer: A

 

NEW QUESTION 30
What are customers able to scope in SAP S/4HANA Cloud with Central Business Configuration (CBC)?
Note: There are 2 correct Answers to this question.

  • A. Scope extensions
  • B. Countries where business processes will run
  • C. Non-standard scenarios
  • D. Pre-defined scenario bundles
  • E. Public sector processes

Answer: C,D

 

NEW QUESTION 31
Which of the following are customizations that key users can make in the Custom Fields and Logic app to extend the Manage My Timesheet app? Note: There are 2 correct Answers to this question.

  • A. Integrate third-party applications
  • B. Regroup and rename fields
  • C. Add additional fields to forms and tables
  • D. Enable confirmation e-mails

Answer: B,C

 

NEW QUESTION 32
Which functionalities are supported by the SAP Fiori Test Your Processes app? Note: There are 2 correct Answers to this question.

  • A. Import custom test plans
  • B. Create or change test plans
  • C. Migrate test plans for execution
  • D. Remediate failed test scenarios

Answer: B,D

 

NEW QUESTION 33
Which Fiori app enables Project Managers to view and analyze the staffing situation for their projects?

  • A. Utilization Analysis
  • B. Margin Analysis
  • C. Project Profitability Overview
  • D. Project Staffing Analysis

Answer: D

 

NEW QUESTION 34
Which of the following contract types are available when defining how to bill the customer? Note: There are 3 correct Answers to this question.

  • A. Time and expenses
  • B. Periodic services
  • C. Fixed price
  • D. Time based
  • E. Periodic billing

Answer: A,B,C

 

NEW QUESTION 35
In the SAP Best Practices Intercompany Processes - Project-Based Services (16T) scenario, how is the intercompany sales order created?

  • A. Manually for each project engagement
  • B. Manually as a one time activity for each distinct project customer
  • C. Manually as a one time activity in your SAP S/4HANA Cloud tenant
  • D. Manually as a one time activity for each delivering company

Answer: D

 

NEW QUESTION 36
Which of the following does the CDS view I_JournalEntryItemCube allow you to report on? Note: There are 2 correct Answers to this question.

  • A. The customer, functional area, company code and G/L account for project actual amounts and quantities
  • B. Your pricing master data for activity types and service cost levels
  • C. The project manager, project accountant, and project partner for the project actual quantities
  • D. The actual amounts per project, WBS element and G/L account in company code currency

Answer: A,D

 

NEW QUESTION 37
What is the purpose of the Starter system in the SAP S/4HANA Cloud implementation project?

  • A. To demonstrate SAP Best Practices processes in a preconfigured system and identify customer personalization requirements
  • B. To conduct a blueprint workshop to identify all customer requirements for a completely customized solution
  • C. To configure the customer's personalized solution for demonstration and testing during the Realize phase
  • D. To demonstrate the customer's personalized solution, including process flows, the organizational structure, and authorizations

Answer: A

 

NEW QUESTION 38
What are the available methods through which you can fill staging tables in the SAP HANA database of the target system? Note: There are 3 correct Answers to this question.

  • A. XML templates
  • B. SAP Smart Data Access
  • C. SAP HANA Smart Data Integration (SDI)
  • D. Customer's ETL tools
  • E. SAP SQL Anywhere

Answer: A,C,D

 

NEW QUESTION 39
Which technology is used to integrate SAP S/4HANA Cloud with other SAP and non-SAP applications?

  • A. SAP Landscape Transformation Replication Server
  • B. SAP Change and Transport System
  • C. Direct connectivity
  • D. SQLConnect function

Answer: C

 

NEW QUESTION 40
Which of the following are benefits of the SAP Best Practices Event-Based Revenue Recognition - Project-Based Services (1IL) scenario? Note: There are 3 correct Answers to this question.

  • A. Margin calculation
  • B. Reconciliation
  • C. Full transparency
  • D. Real-time reporting

Answer: B,C,D

 